SPS 114 Operational Risk Financial Requirement

APRA's standard requiring super trustees to set money aside so members are protected from losses caused by operational risk: how much to hold, what it can be used for and how to rebuild it.

Intermediate About 15 minutes Last reviewed: 10 October 2026 Checked against sources
Issuer
Australian Prudential Regulation Authority (APRA)
Status
Binding prudential standard. The current version (F2024L01319) has applied since 1 July 2025, replacing the version in force since 1 July 2013. APRA's practice guide SPG 114 explains how APRA expects it to be applied; the guide is not itself enforceable.
Applies to
All RSE licensees (trustees of APRA-regulated super funds).
Main related law
Superannuation Industry (Supervision) Act 1993 (SIS Act): the covenant to maintain and manage financial resources to cover operational risk, as trustee capital, a fund reserve or both (s 52(8)(b)), and the limits on a trustee paying itself back from fund assets for operational risk costs (s 56(2A)).

Put it into practice: Board briefing

Explainer · 1 min 2 s · Narrated, with captions How super funds pay for operational mistakes: the ORFR SPS 114 in brief: why super trustees hold an operational risk financial requirement, the target amount and tolerance limit, what the money can be used for, and how it is rebuilt. Download (MP4, 1.5 MB)
Transcript and description

A voice reads the captions aloud. This lists what appears on screen and the captions, in order.

  1. On screen: Title card: How super funds pay for operational mistakes. The operational risk financial requirement, SPS 114.
  2. On screen: A statement: when things go wrong, other members should not foot the bill. Unit pricing errors, missed contributions or system failures can leave members out of pocket. Operational mistakes can cost members money. Without funds set aside, fixing them could mean taking money from other members.
  3. On screen: A vertical bar shows the money held for operational risk. It fills up to a line marked target amount. A dashed line below it marks the tolerance limit. After an incident, members are paid back and the level drops below the tolerance limit. A replenishment plan then rebuilds the money to the target. Every super trustee must hold money for operational risk. The Board sets a target amount and a lower tolerance limit. If paying members back takes the money below the tolerance limit, the Board must approve a plan to rebuild it.
  4. On screen: Two cards. Usually appropriate: paying members back after an incident, fixing a material weakness, and running a continuity plan after an incident. Generally not: routine projects and upgrades, insurance premiums and levies, and penalties on the trustee. APRA's guide gives examples. Since July 2025 the money can also help prevent incidents, not just pay for them.
  5. On screen: A statement: the target is the trustee's call, with a floor. APRA's guide sets minimum targets that depend on the size of the fund. The trustee sets a prudent target from its own risks. APRA's guide expects at least a minimum that depends on the fund's size.
  6. On screen: End card with the page title, web address and a general information disclaimer.

SPS 114 in plain English

Things go wrong in running a super fund: a unit price is calculated incorrectly, contributions are allocated to the wrong accounts, an administrator's system fails or a fraud gets through. When members lose money because of an operational failure, someone has to pay to put it right. If the trustee had no money set aside, it might have to take the cost from other members' balances, which would be unfair, or delay fixing the problem.

The SIS Act therefore requires every trustee to keep financial resources to cover operational risk (s 52(8)(b)). SPS 114 sets the rules: the trustee decides how much it needs (the target amount), how far the balance can fall before it must be rebuilt (the tolerance limit), where the money is held, and what it can and can't be spent on. The money can sit as a reserve inside the fund, as the trustee's own capital, or a mix of both.

ORFR target amount and tolerance limit A vertical bar shows the level of ORFR financial resources, divided into three zones by two lines. The upper line is the ORFR target amount and the lower line is the tolerance limit. Above the target amount: a material surplus may be reduced, and APRA expects to be engaged before a material reduction. Between the tolerance limit and the target: smaller payments and immaterial fluctuations, such as slight investment underperformance, with no replenishment plan needed. Below the tolerance limit: the Board must approve a replenishment plan before it is implemented, explaining how the shortfall arose, the amounts for each fund, the source of funding and the expected date for meeting the target again. Surplus Normal range Shortfall ORFR target amount (paras 12 to 14) Tolerance limit (para 12(b)) Above the target amount A material surplus may be reduced (para 15(c)). APRA expects to be engaged before a material reduction (SPG 114). Between the tolerance limit and the target Smaller payments and immaterial fluctuations, such as slight investment underperformance: no replenishment plan needed (SPG 114). Below the tolerance limit Board-approved replenishment plan before it is implemented: how the shortfall arose, amounts for each fund, the source of funding and the date the target will be met again (paras 18 to 20).
The target amount and tolerance limit divide the ORFR balance into three zones, with paragraph references to SPS 114.

The requirements, one by one

SPS 114 requirements (2025 version)
TopicWhat SPS 114 requiresPara
Core requirementMaintain, manage and use financial resources to protect members from losses due to operational risks relating to the funds the trustee runs. Operational risk has the meaning used in CPS 230.9
Group policiesIf the trustee uses its corporate group's policies or functions, the Board must approve that and make sure they suit the trustee's business.8
ORFR strategyA strategy for meeting the ORFR that covers, at a minimum: the target amount and tolerance limit and why they are appropriate; when and how the money can be used; how it is held; the investment strategy for any reserve; the replenishment process; the review process; and what happens to the money if the trustee or fund is wound up.10
BoardThe Board approves the ORFR strategy and is ultimately accountable for putting it into effect.11
Target amount and tolerance limitSet a target amount and a tolerance limit below it, on a prudent basis that reflects the trustee's operational risk profile and risk assessments, the permitted uses, and the size, business mix and complexity of its business. APRA may require a different target (within a set time) or tolerance limit.12 to 14
Permitted usesOnly to address operational risks that have caused, or could cause, members a loss or a missed gain; to meet CPS 230 requirements for managing and preventing incidents, including fixing material weaknesses and keeping critical operations within tolerance through severe disruption; or to reduce a material surplus.15
How it is heldA reserve within the fund must be separately identifiable from member accounts and other reserves, and unrestricted and readily available. Trustee capital must be held in a form equivalent to Common Equity Tier 1 (CET1) capital.16, 17
ShortfallBelow the tolerance limit, put in place a replenishment plan and rebuild the resources over a period and in a way that treats members fairly and minimises the risk of poor outcomes. The plan explains how the shortfall arose, the amounts for each fund, how and from where it will be rebuilt, and when the target will be met again.18
Plan approvalThe Board approves the replenishment plan before it is implemented. APRA may require changes if the plan doesn't meet the trustee's duties.19, 20
ReviewReview the target amount and tolerance limit at least annually, and after a material operational risk incident or a material change to the business. Report the findings to the Board.21
Audit and expert reviewInternal and external audit arrangements cover compliance with, and the effectiveness of, the ORFR strategy. APRA may require an external expert's report, paid for by the trustee and given to APRA with the Board's preliminary response within 30 business days.22, 23
Notifying APRANotify APRA before making a material change to the target amount.24

How big should the target be?

SPS 114 doesn't set a number. The trustee must work out a prudent amount from its own operational risks and the uses it expects to need. APRA's practice guide sets out the minimum it expects from a soundly run trustee with an effective risk management framework:

APRA guidance on the minimum ORFR target amount (SPG 114, from 1 July 2025)
Funds under management (all funds the trustee runs)Guidance minimum target
More than $165 billion0.175% of funds under management
$30 billion to $165 billion0.20% of funds under management
Less than $30 billion0.25% of funds under management

APRA's table describes both the middle and lowest bands as including $30 billion. For a defined benefit fund, the guide says the percentage may instead be applied to liabilities for vested benefits.

The guide adds some specific points:

Before July 2025, APRA's guidance expected at least 0.25% of funds under management for every trustee. The lower percentages for larger trustees are guidance on the minimum, not a cap; a trustee's own risk assessment can point to a higher figure.

Try it: guidance minimum and tolerance limit

Illustrative only. The guidance minimum is a floor, not the answer: the trustee must set a prudent target from its own risks (para 13).

What the money can and can't be used for

Examples from APRA's guidance (SPG 114)
APRA considers it appropriate to use the ORFR forAPRA considers it generally not appropriate for
Remediation of losses or missed gains caused by an operational risk incidentRoutine and business-as-usual costs, including building, maintaining or improving the operational risk framework
Fixing a vulnerability or weakness that is a material risk to critical operations, including addressing the root cause of an eventNew systems, processes or technology that are not a response to, or to prevent, an incident, near miss or identified material weakness
Preventing losses and disruption where an identified material weakness, if not addressed, could cause members a lossInsurance premiums, levies, and losses from investment underperformance
Carrying out a business continuity plan, a recovery and exit plan, or an orderly exit from a service provider in response to an operational risk incidentFinancial penalties incurred by the trustee or its directors, or any use that breaches the limits on a trustee being indemnified from the reserve

APRA expects trustees to document in the ORFR strategy the kinds of circumstances in which they would use the money, and to keep records of each use and potential use, including decisions not to use it. Over time those records, together with incident and near-miss data, help test whether the target is right.

The SIS Act backs up the purpose of the reserve. A fund's governing rules can't let the trustee reimburse itself from other fund assets for operational risk costs without first using up the reserve and any other ORFR resources, or recover from the fund money it spent from its own ORFR capital (s 56(2A)).

What changed on 1 July 2025

APRA remade SPS 114 with effect from the day CPS 230 started, and the new version refers to CPS 230 throughout. SPG 114 was updated at the same time.

SPS 114 and SPG 114: before and after 1 July 2025
AreaBefore 1 July 2025From 1 July 2025
Permitted usesPayments to address an operational risk event that caused members a loss or deprived them of a gainAlso preventing and managing incidents under CPS 230 (fixing material weaknesses, keeping critical operations within tolerance) and reducing a material surplus
Setting the targetSet components: an amount for identified operational risks after controls, plus an extra amount for risks not specifically identifiedA prudent basis reflecting the risk profile and risk assessments, the permitted uses, and size, business mix and complexity
Review triggersAnnually, and after a material change in identified risks or the businessAnnually, and after a material operational risk incident or a material change in the business
Notifying APRAWithin 10 business days on any of five triggers, including falling below the tolerance limit and events that may need a material amountBefore a material change to the target amount
External expert's reportGiven to APRA within 10 business daysGiven to APRA with the Board's preliminary response within 30 business days
Guidance minimum (SPG 114)0.25% of funds under management for all trusteesTiered by size: 0.175%, 0.20% or 0.25%

Although the old notification triggers have gone from SPS 114, a material operational risk incident still has to be notified to APRA under CPS 230, within 72 hours of becoming aware of it, and may also be a reportable situation for ASIC (see breach and incident reporting).

Holding, investing and rebuilding the money

Worked example: a unit pricing error and a replenishment plan

A trustee runs one fund with $50 billion in funds under management. The guidance minimum for its size is 0.20%, or $100 million. Because it is midway through moving to a new administration platform, its risk assessment supports a higher target of $110 million, with a tolerance limit of $99 million. The reserve holds $110 million.

  1. A system change at the administrator causes unit prices to be understated for two weeks. Remediating affected members, including lost earnings, costs $14 million. This is a loss caused by an operational risk incident, so it is a permitted use (para 15(a)).
  2. The trustee also assesses the incident under CPS 230 and notifies APRA if it is material, and considers whether it is a reportable situation for ASIC.
  3. After the payment the reserve holds $96 million, below the $99 million tolerance limit, so a replenishment plan is required (para 18).
  4. The plan explains how the shortfall arose, the amount for the fund, how the $14 million will be rebuilt and from what source, and the expected date for reaching the target again. It can take into account a recovery from the administrator under the service agreement if the trustee believes it can reasonably rely on it (SPG 114). The Board approves the plan before it starts (para 19).
  5. Because this was a material operational risk incident, the trustee also reviews whether $110 million is still the right target, and reports the findings to the Board (para 21). If it decides on a materially different target, it tells APRA first (para 24).

Illustrative figures and steps for learning only, not advice about any trustee's obligations. Real decisions about funding sources raise questions of fairness between current and future members that need specialist input.

Common mistakes

How SPS 114 fits with other rules

Questions a board can ask

Frequently asked questions

Is 0.25% of funds under management still the rule?

It was never in the standard itself: it was APRA's guidance on the minimum target. Since 1 July 2025 the guidance minimum depends on the trustee's size (0.175%, 0.20% or 0.25%), and the trustee must still work out a prudent amount for its own risks.

Can the ORFR pay for a new administration system?

Generally not, if it is ordinary investment in systems. APRA's guide says it can be appropriate where the work responds to, or prevents, an operational risk incident or near miss, or fixes an identified material weakness that could cause members a loss.

Does APRA have to be told when the ORFR is used?

SPS 114 now only requires notice before a material change to the target amount. The earlier list of five notification triggers was removed in 2025. Material operational risk incidents must still be notified to APRA under CPS 230.

Sources

  1. Prudential Standard SPS 114 Operational Risk Financial Requirement (F2024L01319, in force from 1 July 2025), official text on the Federal Register of Legislation (checked 10 October 2026); Australian Prudential Regulation Authority, SPS 114 Operational Risk Financial Requirement.
  2. Australian Prudential Regulation Authority, SPG 114 Operational Risk Financial Requirement (current from 1 July 2025; checked 10 October 2026).
  3. Australian Prudential Regulation Authority, superseded SPS 114 (in force 1 July 2013 to 30 June 2025) and SPG 114, used for the comparison table.
  4. Superannuation Industry (Supervision) Act 1993 (Cth), sections 52(8)(b) and 56(2A), compilation in force from 10 August 2026, on the Federal Register of Legislation.

Last reviewed: 10 October 2026 · Next review due: October 2027

Spotted an error or an out-of-date requirement? Suggest a correction (free GitHub account needed). See how we check content.