Human factors and cognitive bias in risk decisions

The predictable ways human judgement goes wrong in risk assessment, escalation and decisions, and practical ways to design processes that counter them, with a calibration test.

Advanced About 26 minutes Last reviewed: 8 October 2026 Checked against sources

The idea in plain English

Risk management relies on human judgement at almost every step: rating likelihood and consequence, deciding whether an incident is serious, choosing whether to escalate, approving a new product. Decades of research show that human judgement is systematically biased in predictable ways, especially under uncertainty, time pressure and social pressure.

The point isn't that people are careless. It's that well-meaning, experienced people make the same kinds of errors, so risk processes need to be designed to counter them. This page covers the biases that matter most in risk work and practical techniques that reduce them.

Try it first: how calibrated are you?

For each question, give a range you are 90% confident contains the true answer. Don't look anything up. If you are well calibrated, about 9 in 10 ranges should contain the answer.

90% confidence ranges

Research on calibration has consistently found that people's "90% ranges" contain the true answer far less often than 90% of the time. The same overconfidence shows up when risk workshops estimate the likelihood of rare events or the range of possible losses.

The biases that matter most in risk work

BiasWhat it isWhere it shows up in risk work
AnchoringEstimates stick close to a starting number, even an irrelevant one.Risk ratings that barely move from last year's register; loss estimates anchored on the first figure mentioned.
AvailabilityJudging likelihood by how easily examples come to mind.Over-rating risks that were recently in the news; under-rating risks that have never happened here.
OverconfidenceRanges and estimates narrower than knowledge justifies.Scenario ranges that are far too tight; confident "remote" likelihood ratings for events with no data.
Optimism biasBelieving bad outcomes are less likely for us than for others.Generous residual ratings; project timelines and benefits that assume everything goes to plan.
GroupthinkCohesive groups suppress dissent to reach agreement.Workshops where the most senior person speaks first and everyone agrees; boards with no challenge.
Normalisation of devianceRepeated exceptions come to be accepted as normal because nothing bad happened.Recurring control exceptions, workarounds and overdue actions treated as business as usual.
Escalation of commitment (sunk cost)Continuing a failing course because of what has already been invested.Troubled projects and system migrations that keep going past the point where stopping was cheaper.
Hindsight and outcome biasAfter the event, outcomes seem predictable, and decisions are judged by results rather than by the quality of the reasoning.Incident reviews that blame individuals; good decisions criticised because of bad luck, and bad ones praised because of good luck.

Techniques that reduce bias

TechniqueHow it worksCounters
Independent first ratingsEach participant rates privately before discussion; the facilitator shows the spread, then the group discusses the differences.Anchoring, groupthink, authority effects
Pre-mortemBefore a decision, imagine it has failed badly and write down why. Proposed by psychologist Gary Klein.Optimism, overconfidence, groupthink
Reference class forecastingStart from how similar projects or events actually turned out, then adjust for specifics.Optimism, planning fallacy
Red teams and devil's advocatesAssign someone the explicit job of challenging the preferred view.Groupthink, confirmation bias
Wider ranges and calibration trainingAsk for ranges, not single points; practise and give feedback on calibration.Overconfidence
Decision checklistsStandard questions before major decisions, such as "What would make us wrong?" and "Who disagrees?"Several biases at once
Kill criteria set in advanceAgree before a project starts what evidence would stop or re-scope it.Escalation of commitment
Judge the decision, not the outcomeReview what was known and reasonable at the time, separately from what happened.Hindsight and outcome bias

Designing bias-resistant risk processes

A note on the evidence

Some well-known findings in behavioural science have failed to replicate, and effect sizes vary between studies and settings. The biases on this page are among the most studied and robust, but treat any single study with care, and focus on process designs that make sense even if a particular effect is smaller than claimed.

Theory and research

Heuristics and biases

The modern study of judgement under uncertainty starts with Tversky and Kahneman (1974). They argued that people estimate probabilities using a few mental shortcuts, or heuristics: judging by resemblance (representativeness), by how easily examples come to mind (availability), and by adjusting from a starting value (anchoring). The shortcuts are usually efficient, but they produce systematic errors, which is what makes them relevant to risk processes. A bias that is predictable can be designed against.

Risk assessment asks people to do exactly what this research shows is hard: put numbers on rare events, judge the likelihood of things that have never happened to them, and estimate ranges for losses. Availability explains why last year's incident dominates this year's workshop. Anchoring explains why ratings barely move from the previous register.

Overconfidence has three forms

Moore and Healy (2008) separate three things that are often all called overconfidence: overestimation (thinking you are better than you are), overplacement (thinking you are better than others) and overprecision (being too sure your estimate is right). Overprecision is the most persistent, and it is the one that matters most for risk work, because it produces the too-narrow "90% ranges" in the calibration exercise above. Earlier calibration research had already found that confidence usually exceeds accuracy, especially on hard questions (Lichtenstein et al., 1982).

The inside view and the planning fallacy

Kahneman and Lovallo (1993) explain a paradox: organisations are often too timid about individual risks, yet too bold in their forecasts. Forecasts are made from an inside view, built up from the plan and its scenarios, which ignores how similar ventures usually turn out. Their remedy is an outside view based on a reference class of comparable cases. Flyvbjerg (2006) turned this into reference class forecasting for projects, showing how optimistic forecasts of cost and benefits arise and how comparing with actual outcomes corrects them. For risk teams, the lesson is to ask "how did projects like this actually go?" before rating the risk of a system migration or product launch.

Commitment, groups and organisations

Some biases operate through people's roles. Staw (1976) found that people who were personally responsible for a failing decision committed more money to it than people who were not, which is why kill criteria agreed in advance help. Groupthink, the suppression of dissent in cohesive groups, comes from Janis (1982); a review of the research that followed found the idea useful but the evidence and methods uneven (Esser, 1998). At the organisational level, Vaughan (1996) showed how small, repeated deviations that cause no harm come to be treated as normal, until they do cause harm. Whether people raise concerns at all depends heavily on psychological safety: in Edmondson (1999), teams that felt safe to take interpersonal risks engaged in more learning behaviour, such as asking for help and discussing errors.

Can bias be reduced?

Telling people about biases does little on its own. Structural fixes, which change the process rather than the person, have the strongest rationale: private ratings before discussion, the premortem (Klein, 2007), reference classes and pre-agreed triggers. There is also some encouraging evidence for training. In two longitudinal experiments, a single session, either a game or an instructional video, produced medium to large reductions in several biases, and the improvements persisted at later follow-up (Morewedge et al., 2015). Hindsight and outcome bias (Fischhoff, 1975; Baron & Hershey, 1988) are especially relevant to reviews and performance assessments, because they lead people to judge decisions by results rather than by the quality of the reasoning.

Applying the techniques: a pre-mortem before go-live

One of the techniques above, applied:

StepWhat happens
Set the sceneThe project team imagines it is six months after go-live of a new member administration system, and the launch has failed badly.
Write independentlyEach person writes down, alone, the reasons it failed. This avoids anchoring and groupthink.
Share and clusterReasons are grouped: data migration errors, call centre overload, an untested rollback plan.
DecideFor each major reason, the team agrees a mitigation or a go/no-go criterion set in advance.
RecordThe results go into the risk register and the go-live decision paper.

Illustrative only.

Frequently asked questions

Can training remove bias?

Training helps people recognise biases but rarely removes them. Process design, such as independent first ratings and pre-set criteria, tends to work better.

Critical perspectives

Seminar questions

  1. Take a risk register you know (or a published example). Which ratings are most likely to be affected by anchoring and availability, and how would you test whether they are?
  2. Moore and Healy argue that overprecision is the most persistent form of overconfidence. Design a way to measure the calibration of a risk team's scenario estimates over time.
  3. Kahneman and Lovallo say organisations are both too timid and too bold. Using an Australian example, such as a large system migration, explain how both can be true at once.
  4. Is the premortem a genuine debiasing technique or a ritual? What evidence would convince you either way?
  5. How could normalisation of deviance show up in a super fund's control environment, and what signals in the data would reveal it before an incident?

Further reading

Check your understanding

1. A workshop's risk ratings barely change from last year's register. Which bias is most likely at work?

2. What is a pre-mortem?

3. Recurring control exceptions come to be treated as normal because nothing has gone wrong yet. This is:

References

Research cited on this page, in APA 7th style. Articles marked peer-reviewed were published in peer-reviewed journals. More in the Research library.

Sources

  1. Calibration answers: Geoscience Australia (river length and mountain height), Australian Bureau of Statistics (2021 Census), Reserve Bank of Australia, APRA.