Change, project and reputational risk
Why so many problems happen during change, how to keep projects honest, and how to manage the reputational fallout of other risks.
Three related risks
| Risk | What it means | Examples |
|---|---|---|
| Change risk | The risk that changing products, systems, processes, structures or providers introduces new risks or breaks existing controls. | A system migration loses member data; a new product launches without the controls it needs; a restructure removes a key reviewer. |
| Project risk | The risk that a project fails to deliver its benefits on time and on budget. | A regulatory program misses its deadline; a technology build runs years late and far over budget. |
| Reputational risk | The risk of losing the trust of customers, members, staff, investors, regulators or the community. | Media coverage of poor treatment of customers; public criticism of an investment; a regulator's enforcement action. |
Change risk
Many major operational failures happen during change, not in steady state. Controls that worked are switched off, data is moved and transformed, staff are learning new processes, and attention is on delivery deadlines. In superannuation, fund mergers (successor fund transfers) and administration platform migrations are high-risk examples: errors can affect many members' balances, insurance and payments at once.
Good practice is to treat material change as a risk event in its own right:
- Assess risk before approving the change, including impacts on critical operations, obligations, controls, data and service providers.
- Involve risk and compliance early, not just at sign-off.
- Test thoroughly, including data reconciliation and parallel running where practical.
- Have go/no-go criteria and a back-out plan.
- Watch closely after go-live (often called "hypercare"), with extra monitoring and quick escalation.
- Update the risk and control registers for the new state.
APRA's CPS 230 expects entities to consider operational risk when making business decisions and to maintain critical operations through change, and APRA's April 2026 letter on AI highlighted change management and assurance as areas needing improvement.
Project risk
Projects fail for familiar reasons: unclear objectives, optimistic plans, changing scope, weak sponsorship, dependency on a few key people or vendors, and reluctance to report bad news. Research on large projects has repeatedly found that cost and schedule overruns are common and that the biggest projects tend to overrun most (Flyvbjerg, 2014).
- Governance: an accountable sponsor, a steering committee with the authority to stop or reshape the project, and stage gates.
- Honest reporting: status based on evidence (milestones actually met) rather than optimism. Beware "watermelon" reporting: green outside, red inside.
- Independent assurance for major programs, from the second line, internal audit or external reviewers.
- Regulatory programs need special care, because the deadline is fixed by law.
Reputational risk
Reputational risk is usually a consequence of other risks, such as conduct failures, operational outages, data breaches or controversial investments, rather than a standalone risk. It matters because trust, once lost, is slow to rebuild, and because it can quickly turn into financial and regulatory consequences, such as customers leaving or regulators intervening.
- Consider it in decisions: ask "how would this look to our members, staff, regulators and the public if it were on the front page?"
- Include it in risk assessments as a consequence dimension on the risk matrix.
- Monitor complaints, social media, media coverage and stakeholder feedback as early warning indicators.
- Prepare crisis communications: who speaks, how quickly, and how customers and members are told.
- Avoid greenwashing and overclaiming. Saying more than you do is itself a reputational (and legal) risk. See Climate-related financial disclosures.
Worked example: moving to a new administration platform
A super fund is moving 400,000 member accounts to a new administrator. The project combines change, project and reputational risk.
- Change risk: data could be lost or corrupted in migration; staff and processes must change at the same time. Controls include trial migrations, reconciliations of every balance, and a rollback plan.
- Project risk: delays and cost overruns. Controls include stage gates where the board decides whether to proceed, independent assurance, and contingency in budget and time.
- Reputational risk: members who can't log in or are paid late will complain, and the media may report it. Controls include member communications before and after, extra call centre capacity, and fast remediation.
- Regulatory: the transition is a material change to critical operations and service providers under CPS 230, and failures may be reportable.
Illustrative only.
Common mistakes
- Go-live dates treated as fixed even when testing isn't finished.
- Risk teams engaged too late, after key design decisions are made.
- Treating reputation as a separate risk to be managed by communications, rather than the result of how other risks are handled.
Questions a board can ask
These are prompts for discussion, not requirements.
- What would make us delay this project, and who decides?
- How will we know quickly if members are being harmed?
- What is our rollback plan, and has it been tested?
Frequently asked questions
Is reputational risk a risk in its own right?
Views differ. Many frameworks treat it as a consequence of other risks, because reputation is damaged by what an organisation does or fails to do. Others list it separately so that it gets attention.
Sources
- Australian Prudential Regulation Authority, Prudential Standard CPS 230 Operational Risk Management and CPG 230.
- Australian Prudential Regulation Authority, APRA calls for a step-change in AI-related risk management and governance (April 2026).
- Flyvbjerg, B. (2014), What you should know about megaprojects and why: an overview, Project Management Journal, 45(2), 6–19.
Last reviewed: 8 October 2026 · Next review due: October 2027